Burundi

 

APPROVAL DATE

July 2008

POWPA ACTIVITIES

2.1.2, 3.1.6

CONTACT PERSON(S)

Mr.Adelin NTNUGNUMBURANYE [inecndg@yahoo.fr]

DOWNLOAD PROJECT DOCUMENT(S)

Burundi POWPA project

 

 

 

 

 

 

 

 


 
     
PHASE I (Round 3)  
         
OUTCOME 1: Promote new models of PA governance and review governance forms  
Specific actions Description Progress snapshot Steps taken this quarter (if any)  
Activity 1.1 Finalize and submit proposals on governance models for government approval 4 = activity completed    
Activity 1.2a Choose 4 pilot PAs 4 = activity completed    
Activity 1.2b Organize meetings and trainings with local communities 4 = activity completed Une réunion de sensibilisation des parties prenantes sur la problématique de gouvernace de l'environnement et des aires protégées a été organisée le 28/8/2009 à Gitega  
Activity 1.2c Develop site management plan 3 = significant progress, nearly complete A l'issu des consultations menées dans quatre sites pilotes choisis sur base du diognostic participatif, quatre plans de gestion et d'aménagement ont été élaborés et finalisés et vont être multipliés.  
Activity 1.2d Strengthen capacity 4 = activity completed    
     
Obstacles faced in implementing Activity 1: Pas d'obstacles  
Lessons learned in implementing Activity 1: L'exercice d'élaboration des quatre plans de gestion a été utile dans la mesure où les cadres de l'INECN et les responsables des sites choisis ont été fortement impliqués à telle enseigne que ils pourront utilisé l'expérience acquise dans l'élaboration des plans de gestion des autres sites qui n'en ont pas.  
         
OUTCOME 2: Establish positive incentive measures for maintaining PAs  
Specific actions Description Progress snapshot Steps taken this quarter (if any)  
Activity 2.1a Analyze possible incentive measures, including private sector incentives 0 = not yet begun, no progress    
Activity 2.1b Develop a menu of potential incentives and describe required regulation 0 = not yet begun, no progress    
Activity 2.1c Hold workshop to discuss proposal 0 = not yet begun, no progress    
Activity 2.1d Select two incentives for demonstration at 2 PAs 0 = not yet begun, no progress    
Activity 2.1e Hold workshops to disucss results and seek approval of incentives 0 = not yet begun, no progress    
     

Reader comments


Author name
Author email
Organization
Comment
 
 
  * We respect your privacy.
Your E-mail address will not appear online when you post a comment, and is only required to encourage genuine comments, and will not be used for other purposes.
We love feedback.
Your comments are welcome and invited, but we reserve the right to delete comments that do not respect United Nations values.