PHASE I (Round 3) |
|
|
|
|
|
|
|
|
OUTCOME 1: Improve PA governance forms and types |
|
|
Specific actions |
Description |
Progress snapshot |
Steps taken this quarter (if any) |
|
|
Activity 1.1 |
Study existing forms and types of PA governance |
2 = activity fully underway |
|
|
|
Activity 1.2 |
Hold workshop to discuss governance recommendations |
1 = just started, limited progress |
|
|
|
Activity 1.3a |
Take stock of legal texts on 10 protected areas |
1 = just started, limited progress |
|
|
|
Activity 1.3b |
Analyze actual PA status |
0 = not yet begun, no progress |
|
|
|
Activity 1.3c |
Propose updating constitution to incorporate appropriate governance type |
0 = not yet begun, no progress |
|
|
|
Activity 1.3d |
Conduct meetings with PA managers and agree on PA constitution amendment |
0 = not yet begun, no progress |
|
|
|
Activity 1.3e |
Agree on actions to put in place at 10 sites to start new governance type |
0 = not yet begun, no progress |
|
|
|
|
|
|
|
Obstacles faced in implementing Activity 1: |
|
|
|
Lessons learned in implementing Activity 1: |
|
|
|
|
|
|
|
|
|
OUTCOME 2: Assess capacity needs and establish training courses |
|
|
Specific actions |
Description |
Progress snapshot |
Steps taken this quarter (if any) |
|
|
Activity 2.1 |
Hire local consultants to develop questionnaire on training needs |
2 = activity fully underway |
|
|
|
Activity 2.2 |
Send questionnaires to relevant protected areas and analyze results |
4 = activity completed |
|
|
|
Activity 2.3 |
Organize educational courses for park managers, including IUCN PA masters course |
2 = activity fully underway |
|
|
|
Activity 2.4 |
National Center to organize logistics for training course |
2 = activity fully underway |
|
|
|
Activity 2.5 |
Hold first round of trainings |
2 = activity fully underway |
|
|
|
Activity 2.6 |
Survey the impacts of the trainings |
0 = not yet begun, no progress |
|
|
|
Activity 2.7 |
Develop and sign a capacity building plan to ensure ongoing training |
3 = significant progress, nearly complete |
|
|
|
|
|
|
|
Obstacles faced in implementing Activity 2: |
|
|
|
Lessons learned in implementing Activity 2: |
|
|
|
|
|
|
|
|
|
OUTCOME 3: Amend protected area legislation |
|
|
Specific actions |
Description |
Progress snapshot |
Steps taken this quarter (if any) |
|
|
Activity 3.1 |
Study all central-level legislation and develop recommendations |
1 = just started, limited progress |
|
|
|
Activity 3.2 |
Discuss results at workshop |
0 = not yet begun, no progress |
|
|
|
Activity 3.3 |
Submit to Government of Guinea for adoption |
0 = not yet begun, no progress |
|
|
|
|
|
|
|
Obstacles faced in implementing Activity 3: |
|
|
|
Lessons learned in implementing Activity 3: |
|
|
|
|
|
|
|
|
|
PHASE 2 (Round 5) |
|
|
OUTCOME 1: Assess and improve management effectiveness |
|
|
Specific actions |
Description |
Progress snapshot |
Steps taken this quarter (if any) |
|
|
Activity 1.1 |
Agree on management effectiveness tool |
1 = just started, limited progress |
|
|
|
Activity 1.2 |
Apply Tracking Tool (METT) to assess 8 of 12 PAs and analyze results |
1 = just started, limited progress |
|
|
|
Activity 1.3a |
Travel to 8 PAs to discuss METT results |
0 = not yet begun, no progress |
|
|
|
Activity 1.3b |
Conduct in-depth training on METT |
0 = not yet begun, no progress |
|
|
|
Activity 1.3c |
Agree on 3-4 year plan of action |
0 = not yet begun, no progress |
|
|
|
Activity 1.3d |
Agree on means and resources for covering management effectiveness gaps |
0 = not yet begun, no progress |
|
|
|
Activity 1.4 |
Refine METT scorecard and submit recommendations to government |
0 = not yet begun, no progress |
|
|
|
|
|
|
|
Obstacles faced in implementing Activity 1: |
|
|
|
Lessons learned in implementing Activity 1: |
|