PHASE I (Round 1) |
|
|
|
|
|
|
|
|
|
|
OUTCOME 1: Integrate PAs into wider landscape and sectoral strategies |
|
|
|
Specific actions |
Description |
Progress snapshot |
Steps taken this quarter (if any) |
|
|
|
Activity 1.1a |
Review literature on PA policies, plans and strategies for integration |
4 = activity completed |
|
|
|
|
Activity 1.1b |
Conduct stakeholders workshop to strategize means of integration |
4 = activity completed |
|
|
|
|
Activity 1.1c |
Compile workshop report |
4 = activity completed |
|
|
|
|
Activity 1.2a |
Review literature on poverty issues in and around PAs |
4 = activity completed |
|
|
|
|
Activity 1.2b |
Visit selected sites; hold meetings |
4 = activity completed |
|
|
|
|
Activity 1.2c |
Write reports and recommend actions to reconcile poverty issues at 3 sites |
3 = significant progress, nearly complete |
|
|
|
|
Activity 1.3a |
Recruit consultants to develop integration strategy |
0 = not yet begun, no progress |
|
|
|
|
Activity 1.3b |
Conduct 3 local workshops in communities and 3 stakeholder workshops |
0 = not yet begun, no progress |
|
|
|
|
Activity 1.3c |
Conduct national validation workshop |
0 = not yet begun, no progress |
|
|
|
|
Activity 1.4a |
Recruit consultants to draft proposal to address poverty issues in and around PAs |
0 = not yet begun, no progress |
|
|
|
|
Activity 1.4b |
Identify funding source for implementation of proposal |
0 = not yet begun, no progress |
|
|
|
|
|
|
|
|
|
Obstacles faced in implementing Activity 1: |
|
|
|
|
Lessons learned in implementing Activity 1: |
|