|
|
|
|
|
|
PHASE I (Round 4) |
|
|
|
|
|
|
|
|
OUTCOME 1: Promote innovative forms of governance |
|
|
Specific actions |
Description |
Progress snapshot |
Steps taken this quarter (if any) |
|
|
Activity 1.1a |
Analyze conservation practices and PA management models |
3 = significant progress, nearly complete |
A draft report on conservation practices and PA management modles has been prepared |
|
|
Activity 1.1b |
Analyze forms of conservation and governance |
3 = significant progress, nearly complete |
Expected to be completed this quarter |
|
|
Activity 1.1c |
Develop report identifying potential forms of governance and recommending change |
3 = significant progress, nearly complete |
An outine of the report discussed and adopted. A draft report on conservation practices and PA management modles under preparation |
|
|
Activity 1.2a |
Organize 3 regional workshops to discuss report |
1 = just started, limited progress |
Planned to carried out in |
|
|
Activity 1.2b |
Draft proposal and action plan on improving PA forms and management arrangements |
1 = just started, limited progress |
More work shall be done after the consultation meetings with local communities |
|
|
Activity 1.3a |
Select 2 pilot sites |
4 = activity completed |
The Project Steering Committee inspected the pilot sites in November 2009 |
|
|
Activity 1.3b |
Organize meetings and trainings of communities and rangers |
2 = activity fully underway |
Project Steering Committee meetings on going. So far 4 meetings held. Regional meetings with local communities planned for January-March 2010 |
|
|
Activity 1.3c |
Amend or develop new management plan |
0 = not yet begun, no progress |
This activity is to be undertaken during the training/consultation of local communities |
|
|
Activity 1.3d |
Provide basic capacity and support to site management |
1 = just started, limited progress |
Planned for January-March 2010 during the meetings with local communities |
|
|
Activity 1.4 |
Incorporate lessons into proposal and action plan and finalize plan |
0 = not yet begun, no progress |
To be done after the action plan and the management plans have been prepared and is planned for July 2010 |
|
|
Activity 1.5a |
Hold policy discussions and revise |
0 = not yet begun, no progress |
PSC to review to Action Plan in July 2010, national review workshop to be held in Aug 2010. Presentation to policy makers -Sept -Oct 2010 |
|
|
Activity 1.5b |
Submit for formal adoption |
0 = not yet begun, no progress |
Planned for Oct-November 2010 |
|
|
|
|
|
|
Obstacles faced in implementing Activity 1: |
Implementing the components of the project at the same time is a challenge. Our understanding was that component on governace would be implemented first followed by the component on valuation of protected areas |
|
|
Lessons learned in implementing Activity 1: |
At first we had two separate PSC for the two components of the project. However the two committees have been merged into one since both components of the project feed into the other for example the two pilot sites shall be used by the two project components. Furthermore, information on governance is also vital for valuation component and vice versa. |
|
|
|
|
|
|
|
|
PHASE 2 (Round 5) |
|
|
OUTCOME 1: Economic values of protected areas |
|
|
Specific actions |
Description |
Progress snapshot |
Steps taken this quarter (if any) |
|
|
Activity 1.1 |
Form project team and select 2 pilot sites |
4 = activity completed |
Criteria for selection was prepared, discussed and approved by the PSC. Selection of the two pilot sites completed |
|
|
Activity 1.2a |
At each site, determine systems, services and valuation method |
3 = significant progress, nearly complete |
Desk review being undertaken. Field work undertaken in in Oct-Dec 2009 |
|
|
Activity 1.2b |
Collect data related to use and non-use value to goods and services |
3 = significant progress, nearly complete |
Desk review being undertaken. Fieldwork undertaken in October -December 2009 |
|
|
Activity 1.2c |
Analyze data to determine economic value of goods and services |
3 = significant progress, nearly complete |
Baselin data collected. Analysis on-going |
|
|
Activity 1.2d |
Compare results under a different conservation scenario |
2 = activity fully underway |
Data/information has been collected from the different project sites and analysis of results is on-going |
|
|
Activity 1.3a |
Analyze contribution of PAs to development objectives |
1 = just started, limited progress |
More data collection and analysis to be done |
|
|
Activity 1.3b |
Analyze results on major trends in current and planned PA resource use |
1 = just started, limited progress |
More data collection and analysis to be done |
|
|
Activity 1.3c |
Analyze patterns of income distribution |
2 = activity fully underway |
More data collection and analysis to be done |
|
|
Activity 1.4 |
Develop report on value of PAs to local economy and recommendations |
1 = just started, limited progress |
Results of analysis above to be used to prepare the report on the value of PA to local economy and thereform draw conclusions and recommendations |
|
|
Activity 1.5 |
Present findings in national workshop |
0 = not yet begun, no progress |
Planned for Febraury-March 2010 |
|
|
Activity 1.6 |
Submit recommendations to government for approval |
0 = not yet begun, no progress |
Planned for April-May 2010 |
|
|
|
|
|
|
Obstacles faced in implementing Activity 1: |
Implementing the components of the project at the same time is a challenge. Our understanding was that component on governace would be implemented first followed by the component on valuation of protected areas |
|
|
Lessons learned in implementing Activity 1: |
At first we had two separate PSC for the two components of the project. However the two committees have been merged into one since both components of the project feed into the other for example the two pilot sites shall be used by the two project components. Furthermore, information on governance is also vital for valuation component and vice versa. |